Address: 285 Jay Street at Johnson St
Fire on the 1st floor of a 7 story 100x325 building under construction (College of Technology).
0749 - E-207 - Transmit the 10-75.
TL-105 FAST
0751 - Bn. 31 - All Hands for construction material on fire between the 1st floor and basement, behind a scaffolding. 1 L/S/O, searches in progress.
0753 - Div. 11 - Start out another Tower Ladder to replace TL-105 as FAST (TL-119).
0800 - Div. 11 - We have small pockets of fire at a construction site. Fire is below grade. All construction workers have been accounted for. DWH
0812 - Div. 11 - Still extinguishing small pockets of fire in the foundation. This will be an extended operation.
0822 - Div. 11 - We are going to release the Rescue and Squad. PWH - Duration 36 minutes.
0858 - Div. 11 - All fire has been extinguished. Under Control - Duration 1 hour 12 minutes.
Maybe:
E-207, 205, 224, 226
L-110, 118, 105, 119 s/c FAST
B-31, 32
S-1
R-2
D-11
RAC-2
Command Tac.
Fire on the 1st floor of a 7 story 100x325 building under construction (College of Technology).
0749 - E-207 - Transmit the 10-75.
TL-105 FAST
0751 - Bn. 31 - All Hands for construction material on fire between the 1st floor and basement, behind a scaffolding. 1 L/S/O, searches in progress.
0753 - Div. 11 - Start out another Tower Ladder to replace TL-105 as FAST (TL-119).
0800 - Div. 11 - We have small pockets of fire at a construction site. Fire is below grade. All construction workers have been accounted for. DWH
0812 - Div. 11 - Still extinguishing small pockets of fire in the foundation. This will be an extended operation.
0822 - Div. 11 - We are going to release the Rescue and Squad. PWH - Duration 36 minutes.
0858 - Div. 11 - All fire has been extinguished. Under Control - Duration 1 hour 12 minutes.
Maybe:
E-207, 205, 224, 226
L-110, 118, 105, 119 s/c FAST
B-31, 32
S-1
R-2
D-11
RAC-2
Command Tac.