Address: 40 West 17 Street - between 5 & 6 Avenue
Fire on the 9th floor of a 12 story 50x100 MD.
0733 - Bn. 7 - 10-75.
L-24 FAST - E-1 4th Engine
0734 - Bn. 7 - Transmit the 10-77, fire in a 12 story loft building.
0736 - Bn. 7 - It appears that the sprinkler knocked down the fire. Stretching a line. Attack stair "A".
0740 - Bn. 7 - All Hands
0743 - Bn. 7 - PWH - Duration 18 minutes.
0747 - Div. 1 - Primaries are complete and negative in the fire apartment, Apt 9A. The the apartment was vacant. Sprinklers knocked down the fire, we had 1 L/S/O. Trucks continue to open up.
0754 - Div. 1 - Secondaries are negative, there was no extension. Under Control - Duration 28 minutes.
Assignment:
E-3, 14, S18, 1, 26, 24 CFRD, 16 HRN
B-12, 3, 24 FAST, 5, 7
B-7, 6, 2, 9 Safety
S-1
R-1
D-1
FC, FCB, SB. RB
E-22 w/ High Rise 2
RAC-1
Fire on the 9th floor of a 12 story 50x100 MD.
0733 - Bn. 7 - 10-75.
L-24 FAST - E-1 4th Engine
0734 - Bn. 7 - Transmit the 10-77, fire in a 12 story loft building.
0736 - Bn. 7 - It appears that the sprinkler knocked down the fire. Stretching a line. Attack stair "A".
0740 - Bn. 7 - All Hands
0743 - Bn. 7 - PWH - Duration 18 minutes.
0747 - Div. 1 - Primaries are complete and negative in the fire apartment, Apt 9A. The the apartment was vacant. Sprinklers knocked down the fire, we had 1 L/S/O. Trucks continue to open up.
0754 - Div. 1 - Secondaries are negative, there was no extension. Under Control - Duration 28 minutes.
Assignment:
E-3, 14, S18, 1, 26, 24 CFRD, 16 HRN
B-12, 3, 24 FAST, 5, 7
B-7, 6, 2, 9 Safety
S-1
R-1
D-1
FC, FCB, SB. RB
E-22 w/ High Rise 2
RAC-1