Address: 110-26 106 Street off Rockaway Blvd.
Fire on the 2nd floor of a 2 story 15x40 PD.
E-285 transmitted the 10-75.
TL-127 FAST
TL-142, E-293, & Bn. 51 became available from another box after the 10-75 transmission and were added to the incident.
1054 - Bn. 39 - All Hands - Primaries in progress, trucks opening up, 2 lines stretched.
1058 - Div. 13 - Primaries are negative, MBFKD, Release Rescue & Squad. PWH - Duration 15 minutes.
1103 - Div. 13 - Under Control - Duration 20 minutes.
Maybe:
E-285, 308, 294, 293
L-143, 173, 127F, 142
B-39, 51
S-270
R-4
D-13
Fire on the 2nd floor of a 2 story 15x40 PD.
E-285 transmitted the 10-75.
TL-127 FAST
TL-142, E-293, & Bn. 51 became available from another box after the 10-75 transmission and were added to the incident.
1054 - Bn. 39 - All Hands - Primaries in progress, trucks opening up, 2 lines stretched.
1058 - Div. 13 - Primaries are negative, MBFKD, Release Rescue & Squad. PWH - Duration 15 minutes.
1103 - Div. 13 - Under Control - Duration 20 minutes.
Maybe:
E-285, 308, 294, 293
L-143, 173, 127F, 142
B-39, 51
S-270
R-4
D-13