Address: 420 Lexington Ave. between East 43 & East 44 Street
Electrical fire on a setback roof of a 32 story 100x100 office building.
*Two separate boxes were sent to what turned out to be one fire. Box #0789 was the first box that went out and Box #0793 was second. This rundown reflects both boxes. It sounded as if most (if not all) companies from the first box remained on scene after Battalion 8 transmitted the 10-18.
2025 - E-8 - Using 1x2 investigating an electrical fire on the 19th floor. This may be related to the 9th Battalion box.
2029 - Bn. 8 - Make Box #0789 a 10-18 for a 10-31. Please assign TL-7 to the other box.
2039 - Bn. 9 - We had some overheated feeder cables going to the water tower on the roof. Units venting at this time.
2042 - Bn. 9 - All Hands for an electrical condition in the conduit from the top floor to the roof. Stretching a line now. DWH
L-3 FAST - E-21 4th Engine
2048 - Bn. 9 - We have fire on the setback between the 7th and 8th floor. Engine 65 has a lines stretched and is pouring water onto it now.
Box #0789:
E-8, 21, 65
L-2, 7
B-8
Box #0793
E-16, 26, 54
L-4, 3F
B-9
S-18
R-1
D-3
RAC-1
Electrical fire on a setback roof of a 32 story 100x100 office building.
*Two separate boxes were sent to what turned out to be one fire. Box #0789 was the first box that went out and Box #0793 was second. This rundown reflects both boxes. It sounded as if most (if not all) companies from the first box remained on scene after Battalion 8 transmitted the 10-18.
2025 - E-8 - Using 1x2 investigating an electrical fire on the 19th floor. This may be related to the 9th Battalion box.
2029 - Bn. 8 - Make Box #0789 a 10-18 for a 10-31. Please assign TL-7 to the other box.
2039 - Bn. 9 - We had some overheated feeder cables going to the water tower on the roof. Units venting at this time.
2042 - Bn. 9 - All Hands for an electrical condition in the conduit from the top floor to the roof. Stretching a line now. DWH
L-3 FAST - E-21 4th Engine
2048 - Bn. 9 - We have fire on the setback between the 7th and 8th floor. Engine 65 has a lines stretched and is pouring water onto it now.
Box #0789:
E-8, 21, 65
L-2, 7
B-8
Box #0793
E-16, 26, 54
L-4, 3F
B-9
S-18
R-1
D-3
RAC-1