1426 - Bn. 10 - Using 2x2 for a small fire on the 3rd floor.  1 L/S, Trucks opening up.

1428 - Bn. 10 - Go with the 10-75.  We have smoke increasing in the utility shaft.  Searching for the seat of the fire.

L-43 FAST

1433 - Bn. 10 - All Hands - 1 L/S/O, Engine 39 is hooking up to the standpipe and stretching a line to the floor above.

1442 - Bn. 10 - We have water on the fire in the pipe chase on the 3rd floor.  Trucks continue to open up.  DWH

1446 - Div. 3 - Fire is knocked down, primaries are complete and negative throughout, all workers are accounted for.

1449 - Div. 3 - Secondaries in progress.  PWH - Duration 36 minutes.

1455 - Div. 3 - Secondaries are negative.  Under Control - Duration 41 minutes.