- Joined
- Aug 5, 2015
- Messages
- 4,368
Address: 45 Sutton Place South at East 55th St.
Fire in the elevator machinery room on the roof of a 21 story 100x75 class 1 MD
Phone Alarm - Reporting smoke on the 17th floor - 19:58
Box loaded up due to calls - 19:59
B-8: Urgent 10-77 - Heavy smoke pushing from the roof level - 20:01
L-4 FAST, E-44 HRN, E-65 CFR, B-6 Safety, TL-115 VSU
B-8: All the elevators are inoperable, units are making their way up - 20:03
B-8: We have fire in the elevator machinery room at the roof level - 1 L/S/O - Awaiting Con Ed to shut power - 20:09
D-3: 3 L/S, 1 L/O - Fire in the elevator machinery room with arching that's extending in the stairwell - 20:29
FC: Per D-3, Transmit a 2nd Alarm - 20:30
B-45 (act. 8) RUL, E-263 Communications, E-9 w/ Sat. 1, E-3 w/ HR-1
FC: Special call a Staging Chief (B-7?) - 20:35
FC: Special call an additional Vent Support Ladder (TL-17) - 20:42
FC: Special call 2 additional trucks (H&L-5 act. 4 & TL-15 act. 7) - 20:48
FC: MBFKD - DWH - 21:00
FC: Special call 2 additional trucks (L-26 act. & TL-12) - 21:09
FC: Per C-4c, AVFKD - We still have a heavy smoke condition throughout the building - 21:20
FC: Per C-4c, PWH - 21:22
FC: Under Control - 21:55
Duration: 1 Hour & 59 Min.
Maybe:
E-8, 39, 21, 23, 44N, 65C
L-2, 16, 4F, 7, 35
B-8, 9, 10, 6S
R-1
SQ-18
D-3
FC, SB, RB
TL-115 VSU
RAC-1, RM
M-6, MB
2nd Alarm Maybe:
E-312 (act. 8), 54, 16, 35 (act. 39)
L-136 (act. 2), 28 (act. 4), 5 (act. 4) s/c, 15 (act. 7) s/c, 26 (act.) s/c, 12 s/c
B-1 (act. 9), 45R (act. 8), 7 Staging, 39 Air Recon
MSU, CTU
E-263 Communications
E-9 w/ Sat. 1
E-3 w/ HR-1
TL-17 VSU s/c
Car-4c
Relocations:
E-312 to E-8
E-35 to E-39
E-239 to E-9
E-224 to E-3
E-211 to E-16
E-47 to E-54
L-136 to L-2
L-28 to L-4
L-5 to L-4
L-59 to L-4
L-108 to L-5
L-15 to L-7
L-105 to L-7
SQ-288 to R-1
B-45 to B-8
B-1 to B-9
B-32 to B-9
B-26 to B-8
B-52 to B-6
Fire in the elevator machinery room on the roof of a 21 story 100x75 class 1 MD
Phone Alarm - Reporting smoke on the 17th floor - 19:58
Box loaded up due to calls - 19:59
B-8: Urgent 10-77 - Heavy smoke pushing from the roof level - 20:01
L-4 FAST, E-44 HRN, E-65 CFR, B-6 Safety, TL-115 VSU
B-8: All the elevators are inoperable, units are making their way up - 20:03
B-8: We have fire in the elevator machinery room at the roof level - 1 L/S/O - Awaiting Con Ed to shut power - 20:09
D-3: 3 L/S, 1 L/O - Fire in the elevator machinery room with arching that's extending in the stairwell - 20:29
FC: Per D-3, Transmit a 2nd Alarm - 20:30
B-45 (act. 8) RUL, E-263 Communications, E-9 w/ Sat. 1, E-3 w/ HR-1
FC: Special call a Staging Chief (B-7?) - 20:35
FC: Special call an additional Vent Support Ladder (TL-17) - 20:42
FC: Special call 2 additional trucks (H&L-5 act. 4 & TL-15 act. 7) - 20:48
FC: MBFKD - DWH - 21:00
FC: Special call 2 additional trucks (L-26 act. & TL-12) - 21:09
FC: Per C-4c, AVFKD - We still have a heavy smoke condition throughout the building - 21:20
FC: Per C-4c, PWH - 21:22
FC: Under Control - 21:55
Duration: 1 Hour & 59 Min.
Maybe:
E-8, 39, 21, 23, 44N, 65C
L-2, 16, 4F, 7, 35
B-8, 9, 10, 6S
R-1
SQ-18
D-3
FC, SB, RB
TL-115 VSU
RAC-1, RM
M-6, MB
2nd Alarm Maybe:
E-312 (act. 8), 54, 16, 35 (act. 39)
L-136 (act. 2), 28 (act. 4), 5 (act. 4) s/c, 15 (act. 7) s/c, 26 (act.) s/c, 12 s/c
B-1 (act. 9), 45R (act. 8), 7 Staging, 39 Air Recon
MSU, CTU
E-263 Communications
E-9 w/ Sat. 1
E-3 w/ HR-1
TL-17 VSU s/c
Car-4c
Relocations:
E-35 to E-39
E-239 to E-9
E-224 to E-3
E-211 to E-16
E-47 to E-54
L-28 to L-4
L-5 to L-4
L-59 to L-4
L-108 to L-5
L-105 to L-7
SQ-288 to R-1
B-1 to B-9
B-32 to B-9
B-26 to B-8
B-52 to B-6
Last edited: