- Joined
- Aug 5, 2015
- Messages
- 4,323
Address: 6 Chatham Square off Mott St.
Fire in a restaurant on the first floor with extension to the upper floors of a 4 story 25x75 mixed occupancy & extension to exposure 4 (high rise MD)
Phone Alarm - Reporting smoke on the 3rd floor - 23:47
B-4: Transmit a 10-75 - Fire on the first floor in the rear of the restaurant - 23:51
L-8 FAST
B-4: 1 L/S/O - DWH - 23:55
D-1: Special call an additional truck (H&L-20) - We have fire in the ductwork & in the ceiling & in a closet in the rear - 00:04
D-1: All Hands - Searches in progress - 00:10
D-1: Transmit a 2nd Alarm - Fire on the first & 2nd floors - 00:12
B-31 RUL, B-2 Safety, E-207 w/ Sat. 6
D-1: MBFKD on the first floor - Water on the fire on the 2nd floor - We also have a line stretched to the roof - 00:23
D-1: AVFKD on the first floor - Getting water on small pockets of fire on the 2nd floor - 00:37
D-1: Transmit a 3rd Alarm - 00:40
Staging: Bowery & Bayard St.
B-45 (act. 4) Staging, B-39 Air Recon, E279 Communications
D-1: Fire now on the 2nd & 3rd floors - 00:53
D-1: Transmit the 4th Alarm - We're pulling everyone out of the building & switching to an exterior attack - 01:09
FC: Have the first 2 engines & trucks on the 4th Alarm respond to 14 Mott St. & stretch a 2½ to the roof - 01:14
FC: Fire throughout - Roll call has been conducted, all members are accounted for - We established an exposure 3 sector, we're going to hit fire from the exterior - 01:18
FC: Special call 3 trucks, 1 of them to relieve the FAST truck (L-11, 12, 117F act. 1) - 01:37
FC: 3 TL's in operation - 4 L/S, 3 L/O from exposure 3 - Members have been evacuated from exposure 2 due to possibility of collapse of the fire building - Having difficulty hitting the seat of the fire - 01:48
FC: Transmit a 5th Alarm - We need a full 5th Alarm assignment - 02:18
FC: Special call a new FAST truck, they should respond to 14 Mott. (TL-23 act. 15) - 03:19
FC: Special call 1 additional FAST truck (TL-9) to the C/P, we're gonna have 2 FAST trucks - 03:21
FC: Per C-3, 3 TL's operating to the front of the fire building, 5 handlines & 1 TL operating in the rear - We had extension to the 5th floor of exposure 4 that has been K/D - We have a precautionary line on the 6th floor of exposure 4 - DWH - 03:26
FC: Special call a vent support unit (HR-2 by E-39) - 03:47
FC: Per C-3, PWH - Special call for relief 3 engines, 3 trucks & 2 BC's, out of the 3 trucks, 2 of them to be TL's, 1 of the TL's to be a 95ft. - 04:20
FC: Under Control - 06:03
Duration: 6 Hours & 17 Min.
Maybe:
E-9, 55, 6, 7
L-6, 1, 8F, 20 s/c
B-4, 6
R-1
SQ-18
D-1
RAC-1
*B-1 on another run, B-2 relocated.
2nd Alarm Maybe:
E-224 (act. 9), 33, 15, 28
L-15
B-7, 31R, 2S
FC, SB, RB, TSU-1, RM, CTU
E-207 w/ Sat. 6
3rd Alarm:
E-239 (act. 9), 1 (act. 7), 4, 10
L-106 (act. 6), 105 (act. 1)
B-1, 45 (act. 4) Staging, 39 Air Recon
MSU
RAC-3
E-279 Communications
Car-4d, 32
4th Alarm:
E-241 (act. 4), 14, 3, 16
L-10, 18, 11 s/c, 12 s/c, 117F s/c
B-35
Car-4, 12, 24b
5th Alarm Maybe:
E-258 (act. 9), 92 (act. 10), 307 (act.55?), 91 (act.6)
L-124 (act. 1), 108 (act. 8)
B-52 (act. 4)
Car-3
Special called above the 5th Alarm:
E-280 (act. 6), 21 (act. 55), 248 (act. 10), 237 (act. 15)
L-119 (act. 1), 2 (act. 2), 23F (act. 15), 9F
B-37 (act. 2)
E-39 w/ HR-2
Relief at 04:20
E-24, 54, 67
L-138 (act.9), 14, 24
B-10, 18 (act. 2)
Relocations:
E-224 to E-9
E-239 to E-9
E-258 to E-9
E-79 to E-9
E-237 to E-15
E-91 to E-6
E-92 to E-10
E-248 to E-10
E-230 to E-10
E-47 to E-33
E-69 to E-3
E-21 to E-55
E-291 to E-55
E-22 to E-16
E-280 to E-6
E-262 to E-28
E-1 to E-7
E-229 to E-7
E-89 to E-23
E-46 to E-39
E-241 to E-4
L-105 to L-1
L-117 to L-1
L-124 to L-1
L-119 to L-1
L-114 to L-1
L-106 to L-6
L-40 to L-6
L-41 to L-18
L-138 to L-9
L-115 to L-9
L-49 to L-24
L-2 to L-20
L-23 to L-15
L-108 to L-8
L-125 to L-8
L-176 to L-108
SQ-41 to R-1
B-37 to B-2
B-45 to B-4
B-52 to B-4
B-18 to B-2
B-42 to B-1
B-27 to B-7
B-16 to B-6
Fire in a restaurant on the first floor with extension to the upper floors of a 4 story 25x75 mixed occupancy & extension to exposure 4 (high rise MD)
Phone Alarm - Reporting smoke on the 3rd floor - 23:47
B-4: Transmit a 10-75 - Fire on the first floor in the rear of the restaurant - 23:51
L-8 FAST
B-4: 1 L/S/O - DWH - 23:55
D-1: Special call an additional truck (H&L-20) - We have fire in the ductwork & in the ceiling & in a closet in the rear - 00:04
D-1: All Hands - Searches in progress - 00:10
D-1: Transmit a 2nd Alarm - Fire on the first & 2nd floors - 00:12
B-31 RUL, B-2 Safety, E-207 w/ Sat. 6
D-1: MBFKD on the first floor - Water on the fire on the 2nd floor - We also have a line stretched to the roof - 00:23
D-1: AVFKD on the first floor - Getting water on small pockets of fire on the 2nd floor - 00:37
D-1: Transmit a 3rd Alarm - 00:40
Staging: Bowery & Bayard St.
B-45 (act. 4) Staging, B-39 Air Recon, E279 Communications
D-1: Fire now on the 2nd & 3rd floors - 00:53
D-1: Transmit the 4th Alarm - We're pulling everyone out of the building & switching to an exterior attack - 01:09
FC: Have the first 2 engines & trucks on the 4th Alarm respond to 14 Mott St. & stretch a 2½ to the roof - 01:14
FC: Fire throughout - Roll call has been conducted, all members are accounted for - We established an exposure 3 sector, we're going to hit fire from the exterior - 01:18
FC: Special call 3 trucks, 1 of them to relieve the FAST truck (L-11, 12, 117F act. 1) - 01:37
FC: 3 TL's in operation - 4 L/S, 3 L/O from exposure 3 - Members have been evacuated from exposure 2 due to possibility of collapse of the fire building - Having difficulty hitting the seat of the fire - 01:48
FC: Transmit a 5th Alarm - We need a full 5th Alarm assignment - 02:18
FC: Special call a new FAST truck, they should respond to 14 Mott. (TL-23 act. 15) - 03:19
FC: Special call 1 additional FAST truck (TL-9) to the C/P, we're gonna have 2 FAST trucks - 03:21
FC: Per C-3, 3 TL's operating to the front of the fire building, 5 handlines & 1 TL operating in the rear - We had extension to the 5th floor of exposure 4 that has been K/D - We have a precautionary line on the 6th floor of exposure 4 - DWH - 03:26
FC: Special call a vent support unit (HR-2 by E-39) - 03:47
FC: Per C-3, PWH - Special call for relief 3 engines, 3 trucks & 2 BC's, out of the 3 trucks, 2 of them to be TL's, 1 of the TL's to be a 95ft. - 04:20
FC: Under Control - 06:03
Duration: 6 Hours & 17 Min.
Maybe:
E-9, 55, 6, 7
L-6, 1, 8F, 20 s/c
B-4, 6
R-1
SQ-18
D-1
RAC-1
*B-1 on another run, B-2 relocated.
2nd Alarm Maybe:
E-224 (act. 9), 33, 15, 28
L-15
B-7, 31R, 2S
FC, SB, RB, TSU-1, RM, CTU
E-207 w/ Sat. 6
3rd Alarm:
E-239 (act. 9), 1 (act. 7), 4, 10
L-106 (act. 6), 105 (act. 1)
B-1, 45 (act. 4) Staging, 39 Air Recon
MSU
RAC-3
E-279 Communications
Car-4d, 32
4th Alarm:
E-241 (act. 4), 14, 3, 16
L-10, 18, 11 s/c, 12 s/c, 117F s/c
B-35
Car-4, 12, 24b
5th Alarm Maybe:
E-258 (act. 9), 92 (act. 10), 307 (act.55?), 91 (act.6)
L-124 (act. 1), 108 (act. 8)
B-52 (act. 4)
Car-3
Special called above the 5th Alarm:
E-280 (act. 6), 21 (act. 55), 248 (act. 10), 237 (act. 15)
L-119 (act. 1), 2 (act. 2), 23F (act. 15), 9F
B-37 (act. 2)
E-39 w/ HR-2
Relief at 04:20
E-24, 54, 67
L-138 (act.9), 14, 24
B-10, 18 (act. 2)
Relocations:
E-239 to E-9
E-258 to E-9
E-79 to E-9
E-91 to E-6
E-92 to E-10
E-248 to E-10
E-230 to E-10
E-47 to E-33
E-69 to E-3
E-291 to E-55
E-22 to E-16
E-262 to E-28
E-229 to E-7
E-89 to E-23
E-46 to E-39
L-105 to L-1
L-117 to L-1
L-124 to L-1
L-119 to L-1
L-114 to L-1
L-40 to L-6
L-41 to L-18
L-115 to L-9
L-49 to L-24
L-23 to L-15
L-108 to L-8
L-125 to L-8
L-176 to L-108
SQ-41 to R-1
B-45 to B-4
B-52 to B-4
B-18 to B-2
B-42 to B-1
B-27 to B-7
B-16 to B-6
Last edited: